MISO-J3391
200.3 MW generation in Coles, IL · In queue since April 2024 · Proposed COD September 2027
200.3 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
MISO-J3391 is a proposed 200.3 MW wind generation project located in Coles County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of April 10, 2024, with a proposed commercial operation date of September 15, 2027. The interconnecting utility is Ameren Transmission Company of Illinois.
The project, which consists of 200.3 MW of wind capacity, is currently listed as active in the MISO queue. The point of interconnection (POI) is the 7CASEY - 7KANSAS 345.0kV line. There is no information available regarding a developer or interconnection agreement status for this project.
Generated from interconnection queue and public data sources
State
IL
County
Coles
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7CASEY - 7KANSAS 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.