MISO-J3412
300 MW generation in Ford, IL · In queue since March 2024 · Proposed COD September 2028
300 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
The proposed MISO-J3412 project is a 300 MW solar generation project located in Ford County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 18, 2024. The proposed commercial operation date is September 1, 2028.
The project, which is being developed within the Ameren Illinois service area, is currently listed as active in the MISO queue. No interconnection agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
IL
County
Ford
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.