Project MISO-J3418 — Project Summary

Queue ID
MISO-J3418
Capacity
220 MW
Technology
Solar
Status
active
Location
Sangamon, IL
Region
MISO
Developer
IA Status

MISO-J3418

MISO-J3418BetaActiveSolarMISOLBNL + Live

220 MW generation in Sangamon, IL · In queue since April 2024 · Proposed COD September 2028

220 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 17, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-15

About

The proposed MISO-J3418 project is a 220 MW solar generation project located in Sangamon County, Illinois. The project, which consists of 220 MW of solar photovoltaic generation, is interconnected to the Ameren Transmission Company of Illinois system.

The project is currently active in the MISO interconnection queue, with an entry date of April 17, 2024, and a proposed commercial operation date of September 15, 2028. The point of interconnection is the 7AUSTIN - 7TURNER 345.0kV substation.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Sangamon

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

AMEREN TRANSMISSION COMPANY OF ILLINOIS

Entity

MISO

Service Type

Point of Interconnection

7AUSTIN - 7TURNER 345.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
ILLINOIS.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3418