MISO-J3418
220 MW generation in Sangamon, IL · In queue since April 2024 · Proposed COD September 2028
220 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
The proposed MISO-J3418 project is a 220 MW solar generation project located in Sangamon County, Illinois. The project, which consists of 220 MW of solar photovoltaic generation, is interconnected to the Ameren Transmission Company of Illinois system.
The project is currently active in the MISO interconnection queue, with an entry date of April 17, 2024, and a proposed commercial operation date of September 15, 2028. The point of interconnection is the 7AUSTIN - 7TURNER 345.0kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Sangamon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7AUSTIN - 7TURNER 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.