Project MISO-J3428 — Project Summary

Queue ID
MISO-J3428
Capacity
200 MW
Technology
Wind
Status
active
Location
Mcpherson, SD
Region
MISO
Developer
IA Status

MISO-J3428

MISO-J3428BetaActiveWindMISOLBNL + Live

200 MW generation in Mcpherson, SD · In queue since March 2024 · Proposed COD August 2028

200 MW

Capacity

1

Components

Wind

2y 2m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryMar 18, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-01

About

MISO-J3428 is a proposed 200 MW wind generation project located in McPherson County, South Dakota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 18, 2024. Montana-Dakota Utilities Co. is the utility associated with the project.

The proposed commercial operation date for MISO-J3428 is August 1, 2028. As of the latest data, the project's interconnection agreement (IA) status is not specified. Recent news coverage of the project is not indicated.

Generated from interconnection queue and public data sources

Project Details

State

SD

County

Mcpherson

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

MONTANA-DAKOTA UTILITIES CO.

Entity

MISO

Service Type

Point of Interconnection

Other_

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.