MISO-J3428
200 MW generation in Mcpherson, SD · In queue since March 2024 · Proposed COD August 2028
200 MW
Capacity
1
Components
Wind
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
MISO-J3428 is a proposed 200 MW wind generation project located in McPherson County, South Dakota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 18, 2024. Montana-Dakota Utilities Co. is the utility associated with the project.
The proposed commercial operation date for MISO-J3428 is August 1, 2028. As of the latest data, the project's interconnection agreement (IA) status is not specified. Recent news coverage of the project is not indicated.
Generated from interconnection queue and public data sources
State
SD
County
Mcpherson
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MONTANA-DAKOTA UTILITIES CO.
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3428