MISO-J3434
200 MW generation in Kandiyohi, MN · In queue since March 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3434 is a proposed 200 MW solar generation project located in Kandiyohi County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 18, 2024. The proposed commercial operation date is September 1, 2028. The interconnecting utility is Missouri River Energy Services - Transmission.
The development project consists of 200 MW of solar photovoltaic generation. It is currently listed as "active" in the MISO queue. The point of interconnection (POI) is Willmar.
Generated from interconnection queue and public data sources
State
MN
County
Kandiyohi
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Entity
MISO
Service Type
—
Point of Interconnection
Willmar
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Willmar Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.