MISO-J3451
120 MW generation in Alcona, MI · In queue since April 2024 · Proposed COD April 2027
120 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J3451 is a proposed solar generation project located in Alcona County, Michigan, with a total capacity of 120 MW. The project, under the utility METC, is an active entry in the Midcontinent Independent System Operator (MISO) interconnection queue, identified as MISO-J3451. The queue entry date is April 5, 2024, with a proposed commercial operation date of April 1, 2027.
The development project consists solely of solar photovoltaic generation, with the entire 120 MW capacity attributed to solar technology. As of the current data, there is no information available regarding an interconnection agreement (IA) status, matching to an existing Energy Information Administration (EIA) plant, or recent news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Alcona
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3451