MISO-J3461
156 MW generation in Muscatine, IA · In queue since April 2024 · Proposed COD May 2028
156 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
MISO-J3461 is a proposed solar generation project located in Muscatine County, Iowa, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 156 MW, is being developed by MidAmerican Energy Co. It consists of 156 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on April 17, 2024, and has a proposed commercial operation date of May 1, 2028. The point of interconnection is at SUB 56 - SUB 89 161.0kV. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
State
IA
County
Muscatine
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
SUB 56 - SUB 89 161.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sub 56
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3461