Project MISO-J3464 — Project Summary

Queue ID
MISO-J3464
Capacity
200 MW
Technology
Solar
Status
active
Location
Story, IA
Region
MISO
Developer
IA Status

MISO-J3464

MISO-J3464BetaActiveSolarMISOLBNL + Live

200 MW generation in Story, IA · In queue since April 2024 · Proposed COD June 2028

200 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 2m

Pre-Study0%
Queue EntryApr 16, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-06-30

About

MISO-J3464 is a proposed solar generation project located in Story County, Iowa, with a total capacity of 200 MW. The project is in the MISO interconnection queue as of April 16, 2024, with a proposed commercial operation date of June 30, 2028. The interconnecting utility is ITC Midwest.

The project, consisting of 200 MW of solar photovoltaic generation, is currently listed as active in the MISO queue. The point of interconnection is Fernald. The developer is not specified in the queue data.

Generated from interconnection queue and public data sources

Project Details

State

IA

County

Story

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ITC MIDWEST

Entity

MISO

Service Type

Point of Interconnection

Fernald

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
POI Substation
Fernald Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.