100 MW generation in Winnebago, WI · In queue since April 2024 · Proposed COD June 2028
100 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3466 is a proposed 100 MW solar generation project located in Winnebago County, Wisconsin. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 16, 2024. The proposed commercial operation date is June 30, 2028.
The project, which is interconnected with American Transmission Company, is currently listed as active in the MISO queue. The point of interconnection is the Sunset Point - Ellinwood 138.0kV line.
Generated from interconnection queue and public data sources
State
WI
County
Winnebago
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Sunset Point - Ellinwood 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- ELLINWOOD
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.