MISO-J3471
150 MW generation in Branch, MI · In queue since April 2024 · Proposed COD November 2028
150 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3471 is a proposed solar generation project located in Branch County, Michigan, with a total capacity of 150 MW. The project consists entirely of solar photovoltaic generation. It is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is November 1, 2028. The interconnecting utility is METC.
The point of interconnection for MISO-J3471 is the WAGNER - BATAVIA 138.0kV substation. As of the latest data, the project is listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Branch
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
WAGNER - BATAVIA 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.