MISO-J3472
200 MW generation in Lapeer, MI · In queue since April 2024 · Proposed COD November 2028
200 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
MISO-J3472 is a proposed 200 MW solar generation project located in Lapeer County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 17, 2024. The proposed commercial operation date is November 1, 2028. The interconnecting utility is ITC.
The project is currently listed as "active" in the MISO queue. No interconnection agreement (IA) status is available. There is no identified developer or news coverage associated with this proposed project.
Generated from interconnection queue and public data sources
State
MI
County
Lapeer
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3472