MISO-J3479
225 MW generation in Rapides Parish, LA · In queue since April 2024 · Proposed COD February 2027
225 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-28
MISO-J3479 is a proposed solar generation project located in Rapides Parish, Louisiana, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 225 MW, is being developed by CLECO POWER. It consists of 225 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on April 12, 2024, and has a proposed commercial operation date of February 28, 2027. The point of interconnection is at the Hineston substation. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
LA
County
Rapides Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER
Entity
MISO
Service Type
—
Point of Interconnection
Hineston
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Hineston Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3479