MISO-J3481
100 MW generation in Grant, AR · In queue since April 2024 · Proposed COD February 2027
100 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-28
MISO-J3481 is a proposed 100 MW solar generation project located in Grant County, Arkansas. The project is in the MISO interconnection queue as of April 12, 2024, with a proposed commercial operation date of February 28, 2027. The interconnecting utility is Entergy Arkansas.
The project, which is currently listed as active in the queue, consists of 100 MW of solar photovoltaic generation. The point of interconnection is the J1577 Substation.
Generated from interconnection queue and public data sources
State
AR
County
Grant
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
J1577 Sub
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3481