MISO-J3493
200 MW generation in Mcdonough, IL · In queue since April 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
MISO-J3493 is a proposed wind generation project located in McDonough County, Illinois, with a total capacity of 200 MW. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 17, 2024. The proposed commercial operation date is September 15, 2028.
The project is being developed within the Ameren Transmission Company of Illinois utility territory. As of the current data, the project's interconnection agreement (IA) status is not specified. The project has appeared in recent news coverage regarding renewable energy development in the MISO region.
Generated from interconnection queue and public data sources
State
IL
County
Mcdonough
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN TRANSMISSION COMPANY OF ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3493