MISO-J3497
200 MW storage in Pulaski, IL · In queue since April 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3497 is a proposed 200 MW battery storage project located in Pulaski County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 17, 2024. The proposed commercial operation date is September 30, 2028.
The project, which is interconnected with Ameren Illinois, consists solely of battery storage. As of the current data, the project's interconnection agreement (IA) status is not specified. The developer is not listed in the data.
Generated from interconnection queue and public data sources
State
IL
County
Pulaski
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3497