MISO-J3498
300 MW generation in Knox, IL · In queue since April 2024 · Proposed COD September 2028
300 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
MISO-J3498 is a proposed solar generation project located in Knox County, Illinois, within the Midcontinent Independent System Operator (MISO) region. The development project, with a total capacity of 300 MW, is being proposed to Ameren Illinois. It entered the MISO interconnection queue on April 13, 2024, with a proposed commercial operation date of September 15, 2028.
The project consists of 300 MW of solar photovoltaic generation. It is currently listed as an active project in the MISO interconnection queue, and will interconnect at the 7FARGO - 7SANDBURG 345.0kV point of interconnection.
Generated from interconnection queue and public data sources
State
IL
County
Knox
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7FARGO - 7SANDBURG 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.