MISO-J3505
150 MW storage in Bollinger, MO · In queue since April 2024 · Proposed COD September 2028
150 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3505 is a proposed 150 MW battery storage project located in Bollinger County, Missouri. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 16, 2024. Ameren Missouri is the utility associated with the project.
The proposed commercial operation date for MISO-J3505 is September 30, 2028. The point of interconnection is the 5HERITAGE - 5FREDTN 161.0kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
MO
County
Bollinger
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
5HERITAGE - 5FREDTN 161.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.