MISO-J3518
300 MW storage in Gasconade, MO · In queue since April 2024 · Proposed COD October 2028
300 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
MISO-J3518 is a proposed 300 MW battery storage project located in Gasconade County, Missouri. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 19, 2024. Ameren Missouri is the utility associated with the project. The proposed commercial operation date is October 31, 2028.
The development project consists entirely of battery storage, with a total capacity of 300 MW. The point of interconnection (POI) is Bland.
Generated from interconnection queue and public data sources
State
MO
County
Gasconade
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN MISSOURI
Entity
MISO
Service Type
—
Point of Interconnection
BLAND
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Bland Substation