MISO-J3521
350 MW generation in Shelby, IL · In queue since April 2024 · Proposed COD September 2028
350 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
The proposed MISO-J3521 project is a 350 MW wind generation facility located in Shelby County, Illinois. Interconnecting to Ameren Illinois via the 7NEOGA - 7HOLLAND 345.0kV point of interconnection, the project entered the MISO interconnection queue on April 18, 2024. The proposed commercial operation date is September 15, 2028.
The development project consists of 350 MW of wind capacity. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
State
IL
County
Shelby
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7NEOGA - 7HOLLAND 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.