MISO-J3523
115 MW storage in Barron, WI · In queue since April 2024 · Proposed COD September 2028
115 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3523 is a proposed 115 MW battery storage project located in Barron County, Wisconsin. The project is being developed within the Dairyland Power Cooperative service territory and interconnected to the MISO grid at the Barron - Washco 161.0kV point of interconnection.
The project entered the MISO interconnection queue on April 16, 2024, with a proposed commercial operation date of September 30, 2028. As of the current data, the project is listed as active in the interconnection queue and no Interconnection Agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
WI
County
Barron
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DAIRYLAND POWER COOPERATIVE
Entity
MISO
Service Type
—
Point of Interconnection
BARRON - WASHCO 161.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3523