MISO-J3529
80 MW generation in Mahnomen, MN · In queue since May 2024 · Proposed COD May 2028
80 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-30
MISO-J3529 is a proposed solar generation project located in Mahnomen County, Minnesota, with a total capacity of 80 MW. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on May 20, 2024. The proposed commercial operation date is May 30, 2028. Otter Tail Power Company is the interconnecting utility.
The project consists of 80 MW of solar photovoltaic generation. As of the latest data, the project's interconnection agreement (IA) status is not available. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MN
County
Mahnomen
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Mahnomen - Winger 115.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3529