MISO-J3539
116.9 MW generation in Alcona, MI · In queue since March 2024 · Proposed COD April 2027
116.9 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
MISO-J3539 is a proposed solar generation project located in Alcona County, Michigan, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 116.9 MW, consists entirely of solar photovoltaic technology. The queue entry date is March 28, 2024, with a proposed commercial operation date of April 1, 2027. The interconnecting utility is METC.
The point of interconnection (POI) is the Alpena - Spruce Road 138.0kV line. As of the latest data, the project is listed as active in the MISO interconnection queue. There is no information available regarding an interconnection agreement (IA) status or news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Alcona
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
ALPENA - SPRUCE ROAD 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3539