MISO-J3543
150 MW storage in Dakota, MN · In queue since April 2024 · Proposed COD June 2028
150 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3543 is a proposed 150 MW battery storage project located in Dakota County, Minnesota. The project, under development by Great River Energy, entered the Midcontinent Independent System Operator (MISO) interconnection queue on April 18, 2024. The proposed commercial operation date is June 30, 2028.
The project consists of 150 MW of battery storage. The point of interconnection is the Chub Lake 115 kV substation. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MN
County
Dakota
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
—
Point of Interconnection
Chub Lake 115 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Chub Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3543