Project MISO-J3545 — Project Summary

Queue ID
MISO-J3545
Capacity
200 MW
Technology
Solar
Status
active
Location
Ionia, MI
Region
MISO
Developer
IA Status

MISO-J3545

MISO-J3545BetaActiveSolarMISOLBNL + Live

200 MW generation in Ionia, MI · In queue since April 2024 · Proposed COD September 2028

200 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-15

About

MISO-J3545 is a proposed 200 MW solar generation project located in Ionia County, Michigan. The project, interconnected within the Midcontinent Independent System Operator (MISO) region, entered the MISO queue on April 15, 2024, with a proposed commercial operation date of September 15, 2028. The interconnecting utility is METC.

The project consists of 200 MW of solar photovoltaic generation. It is currently listed as active in the MISO interconnection queue. The point of interconnection is the Bingham - Marquette 138 kV line.

Generated from interconnection queue and public data sources

Project Details

State

MI

County

Ionia

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

METC

Entity

MISO

Service Type

Point of Interconnection

BINGHAM - MARQUETTE 138.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MICHIGAN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.