Project MISO-J3601 — Project Summary

Queue ID
MISO-J3601
Capacity
200 MW
Technology
Solar
Status
active
Location
Morehouse Parish, LA
Region
MISO
Developer
IA Status

MISO-J3601

MISO-J3601BetaActiveSolarMISOLBNL + Live

200 MW generation in Morehouse Parish, LA · In queue since April 2024 · Proposed COD September 2028

200 MW

Capacity

1

Components

Solar

2y 1m

In Queue

IA Status

COD target: 2028

Interconnection

Total Duration

4y 5m

Pre-Study0%
Queue EntryApr 16, 2024

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-01

About

MISO-J3601 is a proposed solar generation project with a total capacity of 200 MW. The project is located in Morehouse Parish, Louisiana, and is being developed within the Entergy Louisiana service area. It entered the MISO interconnection queue on April 16, 2024, with a proposed commercial operation date of September 1, 2028.

The project is currently listed as active in the MISO queue. The point of interconnection is the Oak Ridge (LA) - Swartz 115.0kV substation.

Generated from interconnection queue and public data sources

Project Details

State

LA

County

Morehouse Parish

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

ENTERGY LOUISIANA

Entity

MISO

Service Type

Point of Interconnection

OAK RIDGE (LA) - SWARTZ 115.0kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
LOUISIANA.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J3601