MISO-J3604
650 MW generation in Sullivan, IN · In queue since April 2024 · Proposed COD September 2027
650 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
MISO-J3604 is a proposed 650 MW natural gas generation project located in Sullivan County, Indiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is September 1, 2027. Duke Energy Indiana is the utility associated with the project.
The point of interconnection for MISO-J3604 is the Merom (HED) - Dresser 345.0kV substation. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
State
IN
County
Sullivan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Merom (HED) - Dresser 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3604