MISO-J3611
140 MW generation in Hamilton, IL · In queue since April 2024 · Proposed COD December 2026
140 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
MISO-J3611 is a proposed 140 MW solar generation project located in Hamilton County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. The proposed commercial operation date is December 30, 2026. The interconnecting utility is Ameren Illinois.
The project, which is currently listed as active in the queue, consists of 140 MW of solar photovoltaic generation. The point of interconnection is at the 7W_FRFT_E - 7NORRIS 345.0kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Hamilton
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
7W_FRFT_E - 7NORRIS 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3611