MISO-J3619
150 MW generation in Mississippi, AR · In queue since April 2024 · Proposed COD September 2028
150 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
Proposed project MISO-J3619 is a 150 MW solar generation project located in Mississippi County, Arkansas. The project is interconnected within the Midcontinent Independent System Operator (MISO) queue, with an entry date of April 16, 2024. The proposed commercial operation date is September 30, 2028. Entergy Arkansas is listed as the utility.
The project, which consists of 150 MW of solar capacity, is in the active stage of the interconnection queue. The point of interconnection is at the Monette Junction - Paragould 161.0kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AR
County
Mississippi
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS
Entity
MISO
Service Type
—
Point of Interconnection
MONETTE JUNCTION - PARAGOULD 161.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Junction
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3619