MISO-J3630
117 MW hybrid in East Feliciana Parish, LA · In queue since April 2024 · Proposed COD June 2028
117 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-15
MISO-J3630 is a proposed 117 MW hybrid solar and battery energy storage project located in East Feliciana Parish, Louisiana. The project, which consists of 117 MW of solar generation, is in the MISO interconnection queue as of April 18, 2024, with a proposed commercial operation date of June 15, 2028. The interconnecting utility is Entergy Louisiana.
The point of interconnection for MISO-J3630 is the Moler - Colfel 230 kV line. As of the current data, the project is listed as active in the interconnection queue, and no interconnection agreement (IA) status is specified. The developer is not identified in the available data, but the project is located within the Entergy Louisiana service area.
Generated from interconnection queue and public data sources
State
LA
County
East Feliciana Parish
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY LOUISIANA
Entity
MISO
Service Type
—
Point of Interconnection
MOLER - COLFEL 230.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3630