MISO-J3651
150 MW storage in Lenawee, MI · In queue since April 2024 · Proposed COD September 2028
150 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3651 is a proposed 150 MW battery storage project located in Lenawee County, Michigan. The project, which consists entirely of battery storage, is being developed within the Midcontinent Independent System Operator (MISO) region. Its queue entry date is April 16, 2024, with a proposed commercial operation date of September 30, 2028.
The project is currently listed as active in the MISO interconnection queue. The point of interconnection is the BEECHER - KNOWLES 138.0kV line. The utility associated with the project is METC.
Generated from interconnection queue and public data sources
State
MI
County
Lenawee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BEECHER - KNOWLES 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3651