MISO-J3654
150 MW storage in Washtenaw, MI · In queue since April 2024 · Proposed COD June 2028
150 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-J3654 is a proposed 150 MW battery storage project located in Washtenaw County, Michigan. The project is interconnected within the Midcontinent Independent System Operator (MISO) region and is listed in the MISO interconnection queue as of April 5, 2024. The proposed commercial operation date is June 1, 2028.
The project, which consists entirely of battery storage, is currently listed as active in the interconnection queue. The designated point of interconnection (POI) is the SUPERIOR 120 kV substation. The transmission utility is ITC.
Generated from interconnection queue and public data sources
State
MI
County
Washtenaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
SUPERIOR 120 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.SUPP111
- POI Substation
- Superior Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3654