MISO-J3666
378.82 MW generation in Morgan, IN · In queue since April 2024 · Proposed COD September 2028
378.82 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-30
MISO-J3666 is a proposed 378.82 MW gas-fired generation project located in Morgan County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of April 17, 2024, with a proposed commercial operation date of September 30, 2028. The interconnecting utility is Indianapolis Power & Light Company.
The project consists of 378.82 MW of gas-fired generation. The point of interconnection is the Petersburg - Thompson 345.0kV line. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
IN
County
Morgan
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
INDIANAPOLIS POWER & LIGHT COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Petersburg - Thompson 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3666