MISO-J3672
300 MW generation in Traverse, MN · In queue since April 2024 · Proposed COD October 2028
300 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-30
MISO-J3672 is a proposed 300 MW wind generation project located in Traverse County, Minnesota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. Otter Tail Power Company is the listed utility. The proposed commercial operation date is October 30, 2028.
The project is currently listed as active in the MISO queue. No interconnection agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
MN
County
Traverse
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3672