MISO-J3685
100 MW generation in Pike, IL · In queue since April 2024 · Proposed COD September 2028
100 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
The proposed MISO-J3685 project is a 100 MW solar generation facility located in Pike County, Illinois. Interconnection to the Ameren Illinois grid is planned at the 4HULL - 4MEPPEN T 138.0kV point of interconnection. The project entered the MISO interconnection queue on April 17, 2024, and is currently listed as active.
The proposed commercial operation date for the MISO-J3685 project is September 1, 2028.
Generated from interconnection queue and public data sources
State
IL
County
Pike
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4HULL - 4MEPPEN T 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3685