MISO-J3686
190 MW generation in Christian, IL · In queue since April 2024 · Proposed COD September 2028
190 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3686 is a proposed 190 MW solar generation project located in Christian County, Illinois. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 17, 2024. The proposed commercial operation date is September 1, 2028. The interconnecting utility is Ameren Illinois.
The project, which consists of 190 MW of solar capacity, is currently listed as active in the MISO queue. The point of interconnection (POI) is at the 4AUSTIN - 4TAYLORVL 138.0kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
4AUSTIN - 4TAYLORVL 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.