MISO-J3696
225 MW storage in Montcalm, MI · In queue since April 2024 · Proposed COD December 2026
225 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
MISO-J3696 is a proposed 225 MW battery storage project located in Montcalm County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 15, 2024. The proposed commercial operation date is December 30, 2026. The interconnecting utility is METC.
The project, which consists entirely of battery storage, is currently listed as active in the MISO queue. The point of interconnection is the Nelson Road - Vergennes 345 kV line. There is no indication of an interconnection agreement or news coverage available in the provided data.
Generated from interconnection queue and public data sources
State
MI
County
Montcalm
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
NELSON ROAD - VERGENNES 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.