MISO-J3699
300 MW generation in Henry, IL · In queue since April 2024 · Proposed COD April 2028
300 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
MISO-J3699 is a proposed 300 MW wind energy project located in Henry County, Illinois. The project, which is being developed by MidAmerican Energy Co., consists of 300 MW of wind generation capacity. It is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 18, 2024. The proposed commercial operation date is April 1, 2028.
The point of interconnection for the project is the Oak Grove 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Henry
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
SUB 39 - OAK GROVE 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sub 39
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3699