MISO-J3701
400 MW generation in Taylor, IA · In queue since April 2024 · Proposed COD April 2028
400 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
The proposed MISO-J3701 project is a 400 MW wind generation facility located in Taylor County, Iowa. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is sponsored by MidAmerican Energy Co. It consists of 400 MW of wind generation capacity.
The project entered the MISO interconnection queue on April 18, 2024, with a proposed commercial operation date of April 1, 2028. The point of interconnection is the ORIENT - NORTHBORO 345.0kV substation. As of the current data, the project's interconnection agreement (IA) status is not specified.
Generated from interconnection queue and public data sources
State
IA
County
Taylor
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
ORIENT - NORTHBORO 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.