180 MW generation in Mitchell, IA · In queue since March 2024 · Proposed COD June 2028
180 MW
Capacity
1
Components
Wind
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3702 is a proposed 180 MW wind generation project located in Mitchell County, Iowa. The project, which is interconnected to Northern States Power Company, entered the MISO queue on March 27, 2024, with a proposed commercial operation date of June 30, 2028.
The development project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
IA
County
Mitchell
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
ADAMS
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Adams Substation