MISO-J3719
200 MW generation in Miami, IN · In queue since March 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3719 is a proposed 200 MW solar generation project located in Miami County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of March 20, 2024. The proposed commercial operation date is September 1, 2028. Duke Energy Indiana is the utility associated with the interconnection.
The project consists of 200 MW of solar photovoltaic generation. Its point of interconnection (POI) is the Greentown - Walton 230 kV line. As of the latest data, the project's interconnection agreement (IA) status is not available.
Generated from interconnection queue and public data sources
State
IN
County
Miami
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Greentown - Walton. 230.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.