MISO-J3722
150 MW generation in Hillsdale, MI · In queue since March 2024 · Proposed COD September 2028
150 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3722 is a proposed solar generation project located in Hillsdale County, Michigan, with a total capacity of 150 MW. The project, under consideration in the Midcontinent Independent System Operator (MISO) interconnection queue, was entered on March 27, 2024, and has a proposed commercial operation date of September 1, 2028. The interconnecting utility is METC.
The project is currently listed as active in the MISO queue. The point of interconnection (POI) is at the COLDWATER - MOORE ROAD 138.0kV substation.
Generated from interconnection queue and public data sources
State
MI
County
Hillsdale
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
COLDWATER - MOORE ROAD 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3722