132 MW generation in Vigo, IN · In queue since April 2024 · Proposed COD September 2028
132 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3724 is a proposed solar generation project located in Vigo County, Indiana, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 132 MW, is being developed by Duke Energy Indiana. It consists of 132 MW of solar photovoltaic generation.
The project entered the MISO interconnection queue on April 16, 2024, and has a proposed commercial operation date of September 1, 2028. The point of interconnection is the Dresser - Wabash River 138.0kV substation. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
IN
County
Vigo
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
DUKE ENERGY INDIANA
Entity
MISO
Service Type
—
Point of Interconnection
Dresser - Wabash River 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Wabash
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3724