MISO-J3725
200 MW generation in Louisa, IA · In queue since April 2024 · Proposed COD September 2028
200 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
MISO-J3725 is a proposed solar generation project located in Louisa County, Iowa, with a total capacity of 200 MW. The project, under consideration by MidAmerican Energy Co., is currently active in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is April 18, 2024, with a proposed commercial operation date of September 1, 2028.
The project consists of 200 MW of solar photovoltaic generation. The point of interconnection is at the SUB 93 LOUISA - SUB T HASKINS 345.0kV substation.
Generated from interconnection queue and public data sources
State
IA
County
Louisa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
—
Point of Interconnection
SUB 93 LOUISA - SUB T HASKINS 345.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Sub T
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3725