MISO-J3735
100 MW storage in Genesee, MI · In queue since April 2024 · Proposed COD June 2028
100 MW
Capacity
1
Components
Battery
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
MISO-J3735 is a proposed 100 MW battery storage project located in Genesee County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 5, 2024. The proposed commercial operation date is June 1, 2028. The interconnecting utility is METC.
The project consists of 100 MW of battery storage. As of the current data, the project's interconnection agreement (IA) status is not specified. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Genesee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BEVERIDGE 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Beveridge Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.