MISO-J3743
175.5 MW generation in Tuscola, MI · In queue since April 2024 · Proposed COD May 2027
175.5 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
MISO-J3743 is a proposed wind generation project located in Tuscola County, Michigan, with a total capacity of 175.5 MW. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 12, 2024. The proposed commercial operation date is May 1, 2027. The interconnecting utility is ITC.
The project, sponsored within the MISO queue by the entity MISO, consists solely of wind generation. As of the latest data, the project's interconnection agreement (IA) status is not specified. The project is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Tuscola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
—
Point of Interconnection
ARROWHEAD
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MP.HVDCE
- POI Substation
- Arrowhead Substation 230/115 kV
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3743