MISO-J3749
200 MW generation in Lyon, MN · In queue since April 2024 · Proposed COD June 2028
200 MW
Capacity
1
Components
Wind
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
MISO-J3749 is a proposed 200 MW wind generation project located in Lyon County, Minnesota. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on April 11, 2024, with a proposed commercial operation date of June 30, 2028. Northern States Power Company is the utility associated with the project.
The project is currently listed as active in the MISO queue. The point of interconnection (POI) is at Lyon County. There is no interconnection agreement (IA) status available in the provided data, nor is there any indication of news coverage or a link to an existing operating plant.
Generated from interconnection queue and public data sources
State
MN
County
Lyon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
LYON COUNTY
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NSP.MARSHSOLAR
- POI Substation
- Lyon County (LYC) Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3749