MISO-J3756
4.2 MW generation in Marquette, MI · In queue since April 2024 · Proposed COD January 2019
4.2 MW
Capacity
1
Components
Gas
2y 1m
In Queue
—
IA Status
COD target: 2019
Total Duration
2y 1m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-01-21
MISO-J3756 is a proposed 4.2 MW gas-fired generation project located in Marquette County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of April 17, 2024. The proposed commercial operation date is January 21, 2019. American Transmission Company is the utility associated with the point of interconnection, named Huron.
The project is currently listed as active in the MISO queue. No developer is specified in the queue data. There is no indication of an executed interconnection agreement or news coverage for this project.
Generated from interconnection queue and public data sources
State
MI
County
Marquette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Huron
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Huron Substation