MISO-J3758
300 MW generation in Macon, MO · In queue since April 2024 · Proposed COD September 2028
300 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-15
MISO-J3758 is a proposed 300 MW solar generation project located in Macon County, Missouri. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on April 18, 2024. The proposed commercial operation date is September 15, 2028.
The project, which is listed under the utility Ameren Illinois, is currently in active status within the MISO queue. No Interconnection Agreement (IA) status is available. The point of interconnection is listed as "Other_". The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MO
County
Macon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMEREN ILLINOIS
Entity
MISO
Service Type
—
Point of Interconnection
Other_
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.