MISO-J3761
145.8 MW generation in Ogemaw, MI · In queue since April 2024 · Proposed COD November 2027
145.8 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-01
MISO-J3761 is a proposed solar generation project located in Ogemaw County, Michigan, with a total capacity of 145.8 MW. The project, which consists entirely of solar photovoltaic generation, is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered on April 5, 2024. The proposed commercial operation date is November 1, 2027.
The project is interconnected to the METC utility grid at the Gallagher-Twining 138.0kV point of interconnection. As of the current data, the project is listed as "active" in the MISO queue, and no Interconnection Agreement (IA) status is specified.
Generated from interconnection queue and public data sources
State
MI
County
Ogemaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
GALLAGHER - TWINING 138.0kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3761