MISO-J3764
170 MW hybrid in Madison, MS · In queue since April 2024 · Proposed COD March 2028
170 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
MISO-J3764 is a proposed 170 MW hybrid solar and battery project located in Madison County, Mississippi. The development project, which consists of 170 MW of solar capacity, is in the MISO interconnection queue as of April 18, 2024, with a proposed commercial operation date of March 1, 2028. The interconnecting utility is Entergy Mississippi, LLC.
The project is currently listed as active in the MISO queue, and will interconnect at the Virlilia Substation 230 kV. There is no indication of an executed interconnection agreement. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MS
County
Madison
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
—
Point of Interconnection
Virlilia Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J3764